ARIZONA HOUSE OF REPRESENTATIVESFifty-sixth Legislature Second Regular Session |
|
HB 2860: water conservation infrastructure; reimbursement
Sponsor: Representative Livingston, LD 28
Committee on Appropriations
Overview
Allows the Arizona State Treasurer (Treasurer) to distribute a maximum of $200,000,000 of specified prime contracting transaction privilege tax (TPT) revenues to a municipality or county for water conservation infrastructure improvements for the benefit of an economic development.
History
The prime contracting TPT classification is comprised of the business of prime contracting and manufactured building dealer. The tax base for the prime contracting classification is 65% percent of the gross proceeds of sales or gross income derived from business with specified deductions as outlined in statute (A.R.S. § 42-5075).
Currently, the Treasurer is required to pay monthly increments to a municipality or county for public infrastructure improvements for the benefit of a manufacturing facility. The monthly increments cannot exceed the total amount of state TPT revenues collected from the prime contracting classification derived from contracts to construct buildings for the benefit of a manufacturing facility or 80% of the total cost of the public infrastructure improvements, whichever is less. The total amount paid to all municipalities and counties cannot exceed $200,000,000 (A.R.S. 42-5032.02).
Provisions
1. Requires the Treasurer to pay monthly increments to a municipality or county for water conservation infrastructure improvements for the benefit of an economic development. (Sec. 6)
2. Prohibits the total amount paid to a municipality or county from exceeding the total amount of state TPT revenues from the prime contracting classification derived from contracts to construct buildings for the benefit of the economic development or 80% of the total cost of public infrastructure improvements, whichever is less. (Sec. 6)
3. Prohibits the total amount paid to all municipalities and counties from exceeding $200,000,000 for water conservation infrastructure. (Sec. 6)
4. Prohibits the Treasurer from making any payments until July 1, 2024, and until 10% of the qualifying capital investment is made by all manufacturing facilities included in the economic development. (Sec. 6)
5. Requires, within 180 days of starting construction of the buildings for the benefit of the economic development necessitating water conservation infrastructure improvements, the manufacturing facility to file a sworn certification with the Arizona Commerce Authority (ACA) and submit a copy to the applicable municipality or county agreeing to:
a) make at least $500,000,000 in capital investment if the manufacturing facility is in a county with a population of 800,000 or more; or
b) make at least $50,000,000 in capital investment if the manufacturing facility is in a county with a population less than 800,000. (Sec. 6)
6. Requires the sworn certification to contain a sworn statement that information contained is true ad correct. (Sec. 6)
7. Requires the manufacturing facility and the municipality or county, before submitting the sworn certification to the ACA, to enter into a written agreement that:
a) identifies and states the costs of the water conservation infrastructure improvements; and
b) identifies the sources of monies that will be used to pay for the water conservation infrastructure improvements. (Sec. 6)
8. Requires the municipality or county, on receipt of the sworn certification from a manufacturing facility, to enter into a written agreement with the Arizona Department of Revenue (DOR). (Sec. 6)
9. Outlines what must be included in the written agreement between the municipality or county and DOR. (Sec. 6)
10. Requires the Treasurer to cease payments to a municipality or county if:
a) the municipality or county has received monies that meet or exceed 80% of the total cost of public infrastructure improvements necessary to support the activities related to the manufacturing facility and the economic development; or
b) the maximum distribution has been met. (Sec. 6)
11. Allows DOR to disclose specified information to an official of any municipality or county in an agreement regarding water conservation infrastructure improvements. (Sec. 1)
12. Adds tax revenues paid to a municipality or county for water conservation infrastructure improvements to the tax distribution base. (Sec. 2)
13. States that a manufacturing facility can satisfy written agreement requirements for water conservation infrastructure improvements and public infrastructure improvements with the same agreement. (Sec. 5, 6)
14. Defines related terms. (Sec. 5, 6)
15. Makes technical and conforming changes. (Sec. 3, 4, 5, 7)
16. Contains a delayed effective date of January 1, 2025. (Sec. 8)
17.
18.
19. ---------- DOCUMENT FOOTER ---------