HB 2192: appropriations; Interstate 10; vehicle lanes
Sponsor: Representative Livingston, LD 28
Caucus & COW
Overview
Increases the FY 2027 and FY 2028 appropriations for the widening of Interstate 10 (I-10) between State Route 85 (SR 85) and Citrus Road from a total of $108,000,000 to $120,000,000 and moves up the appropriations to FY 2026 and FY 2027.
History
Laws 1973, Chapter 146 established the Arizona Department of Transportation (ADOT) to provide for an integrated and balanced state transportation system with a director responsible for the Department's administration (A.R.S. § 28-331). ADOT has exclusive control and jurisdiction over state highways, state routes, state-owned airports and all state-owned transportation systems or modes (A.R.S. § 28-332).
The FY 2023 Budget appropriated $64,200,000 from the State Highway Fund (SHF) in FY 2023 to ADOT for the design and construction of additional vehicle lanes, separated by a lighted median, on I-10 between SR 85 and Citrus Road.
The FY 2024 Budget adjusted the FY 2023 appropriation by supplementing an additional $52,090,000 from the GF in FY 2023 and decreasing the SHF appropriation to $60,910,000. These adjustments resulted in a total of $113,000,000 being appropriated for the I-10 widening project between SR 85 and Citrus Road in FY 2023.
The FY 2025 Budget deferred funding for multiple transportation projects that received appropriations in previous fiscal years. $108,000,000 of FY 2023 funding for the I-10 widening project between SR 85 and Citrus Road was deferred to FY 2027 and FY 2028. $30,000,000 is appropriated from the GF in FY 2027 and $78,000,000 from the GF in FY 2028 for the I-10 widening project between SR 85 and Citrus Road.
Provisions
1. Increases from $30,000,000 to $70,000,000, an existing FY 2027 appropriation from the GF to ADOT for the design and construction of additional vehicle lanes, separated by a lighted median, on I-10 between SR 85 and Citrus Road and moves the appropriation up to FY 2026. (Sec. 1)
2. Decreases from $78,000,000 to $50,000,000, an existing FY 2028 appropriation from the GF to ADOT for the design and construction of additional vehicle lanes, separated by a lighted median, on I-10 between SR 85 and Citrus Road and moves the appropriation up to FY 2027. (Sec. 1)
3. Requires ADOT to procure construction-manager-at-risk or design-build construction services to expedite construction and ensure completion of the I-10 widening project between SR85 and Citrus Road. (Sec. 1)
Amendments
Committee on Appropriations
1. Appropriates $40,000,000, rather than $70,000,000, from the GF in FY 2026 to ADOT for the design and construction of additional vehicle lanes, separated by a lighted median, on I-10 between SR 85 and Citrus Road.
2. Appropriates $93,000,000, rather than $50,000,000, from the GF in FY 2027 to ADOT for the design and construction of additional vehicle lanes, separated by a lighted median, on I-10 between SR 85 and Citrus Road.
3. Removes the requirement for ADOT to procure construction-manager-at-risk or design-build construction services to expedite construction and ensure completion of the I-10 widening project.
4. Requires ADOT to procure construction bids that incorporate the cost-plus-time (A+B) method to expedite construction and ensure completion of the I-10 widening project in a timely manner.