The Arizona Revised Statutes have been updated to include the revised sections from the 56th Legislature, 1st Regular Session. Please note that the next update of this compilation will not take place until after the conclusion of the 56th Legislature, 2nd Regular Session, which convenes in January 2024.
DISCLAIMER
This online version of the Arizona Revised Statutes is primarily maintained for legislative drafting purposes and reflects the version of law that is effective on January 1st of the year following the most recent legislative session. The official version of the Arizona Revised Statutes is published by Thomson Reuters.
40-360.08 - Transfer of certificate; compliance by committee; commission and review panel; authorization to construct
40-360.08. Transfer of certificate; compliance by committee; commission and review panel; authorization to construct
A. Subject to such limitations and conditions as may otherwise be prescribed by law, a certificate may be transferred to any electric company or electric utility agreeing to comply with the terms, limitations and conditions contained therein.
B. If the committee or the commission fails to act on an application within the applicable time period prescribed in this article, the applicant may, in its discretion and in the interest of providing adequate, reliable and economical electric service to its customers, immediately proceed with the construction of the planned facilities at the proposed site or, if application has been made for alternative sites, at the proposed site which in the opinion of the applicant best satisfies the factors expressed in section 40-360.06.