The Arizona Revised Statutes have been updated to include the revised sections from the 56th Legislature, 1st Regular Session. Please note that the next update of this compilation will not take place until after the conclusion of the 56th Legislature, 2nd Regular Session, which convenes in January 2024.
DISCLAIMER
This online version of the Arizona Revised Statutes is primarily maintained for legislative drafting purposes and reflects the version of law that is effective on January 1st of the year following the most recent legislative session. The official version of the Arizona Revised Statutes is published by Thomson Reuters.
The fee to be paid for each application is as follows and shall be paid to the committee for deposit, pursuant to sections 35-146 and 35-147, in a special fund to be known as the utility siting fund:
1. For a new proposed plant site and associated transmission line site, ten thousand dollars.
2. For expansion of an existing plant site and a new proposed transmission line site, seven thousand five hundred dollars.
3. For expansion of an existing plant site only, five thousand dollars.
4. For a new proposed transmission line site one hundred miles or more in length, five thousand dollars.
5. For a new proposed transmission line site over fifty but less than one hundred miles in length, two thousand five hundred dollars.
6. For a new proposed transmission line site fifty miles or less in length, one thousand dollars.
7. For a new proposed transmission line site paralleling an existing transmission line site, regardless of length, one thousand dollars.